Construction of energy efficient buildings – schools and kindergartens

Project Status

Realized projects

Start Date

Realisation Date

TYPE OF FUNDING

BUDGET (DENARS)

Project goals
The main goal of the project is to reduce electricity and heat consumption by replacing windows, doors, insulating floors, roofs and walls and installing an economical heating system in six school buildings in the region. For three schools (in Ohrid, Debarca and Centar Zupa) first technical documentation was prepared – basic projects and audit for performance of measures/interventions. Then we moved on to the concrete implementation of the set of measures to improve energy efficiency in the following municipalities, ie school buildings: Ohrid – Primary School “Kocho Racin” in D. Lakocerej, Kichevo – High School “Mirko Mileski” and High School “Drita”, Debarca- Primary school “Debarca” in Orovnik, Centar Zupa – Primary school “Mustafa Kemal Ataturk” and High school “Ata” and Primary school “Nexhati Zekirija” in Kodzadzik and in Plasnica – Primary school “Yunus Emre” in Lisichani.
In Kindergarten “Planinski cvet” in Vevchani is installed a system of solar collectors, in Kindergarten “8th of March- Sonce” in Struga the old carpentry was replaced with new PVC windows and doors, and in Kindergarten “Jasna Risteska” in Ohrid the roof and the sanitary facilities were repaired, an external thermal facade was installed and the old carpentry was replaced with new PVC windows and doors.

Project results
– Prepared technical documentation – three basic projects with audit for 3 school buildings;
– Insulated under 306 m2, laminate flooring 251 m2, tiles laid 55 m2;
– Insulated ceilings with steam dam and thermal facade on an area of ​​1808 m2;
– Replacement of old ones with 25 energy saving lamps;
– Replacement of old with new PVC carpentry – 24 doors, 82 windows with an area of ​​563 m2;
– Reconstruction of roofs with an area of ​​2126 m2;
– Builded boiler room on an area of ​​61 m2 and installed hot water heating system for 180 users;
– 30% energy savings in all Chilean buildings where EE interventions have been made;
– Placed tiles on an area of ​​278 m2;
– Installed system for sanitary hot water with 3 solar collectors and a boiler of 150l;
– Installed thermal facade on an area of ​​835 m2;
– Replacement of old with PVC carpentry – 23 doors, 104 windows with an area of ​​315 m2;
– Reconstruction of roofs with an area of ​​1030 m2.

Gallery

Partner municipalities: 
Documentation 

Share this project

Share on email
Email
Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on whatsapp
WhatsApp
Share on telegram
Telegram